Material Master Safety Stock and MRP

Material Master Safety Stock  and MRP……
Material Master Safety Stock and MRP_第1张图片
Safety stock
 
    Specifies the quantity whose purpose is to satisfy unexpectedly high
    demand in the coverage period.
 
    The risk of shortfalls is reduced by having a safety stock.
 
Procedure
 
    With manual reorder point planning, you can enter a value in the
    material master record. However, it is merely for information.
 
    With automatic reorder point planning and forecast-based planning, the
    system determines and adjusts the value automatically for forecasting
    purposes.
 
MRP 跟安全库存存在一定的联系。
 
一.第一次创建物料
 
如: R999-100 这个物料是我们刚创建的
       Safetty Stock: 100 PC
 
我们用T-Code: MMBE / MB52
 
因为物料是刚创建,肯定是没有库存, 所以库存 是 0 .
 
通过一系列T-Code:  MK01 创建供应商, T-Code: ME11 创建物料清单
 
完成上面的操作后,我们可以通过 T-Code: MD03 创建采购需求
接着 T-Code: MD04  Run MRP , 我们可能到planing order 已经被创建出来,物料需求就等库存 100 PC.
 
以上是为了满足 Safety Stock 保持 100 自动创建物料需求 Run MRP.
 
 
二.当库存被消耗完,低于安全库存
 
假若库存现在  Material Number: R999-100  Qty: 100 PC
 
现在我们用MIGO , Good Issue , Others , Moventy Type: 502   做一次发货,使库存数量低于安全库存,这里我们将库存数库成 0  PC.
 
T-Code: MB51

这里我们再做 MD03 创建物料需求计划, MD04  Run MRP. 可以看到新的planning Order 又产生了.
 
三. 我们也可以通过 加Forecasting 的方法来产生Run MRP请求

T-Code: MD64  给物料加 Forecasting
 
 
接着: T-Code: MD03 
                            MD04
 
 

我们可以看到,也产生了Run MRP 物料需求计划.
 
 
 
 
 
 