Material Master Safety Stock and MRP

Material Master Safety Stock  and MRP……
Safety stock
 
    Specifies the quantity whose purpose is to satisfy unexpectedly high
    demand in the coverage period.
 
    The risk of shortfalls is reduced by having a safety stock.
 
Procedure
 
    With manual reorder point planning, you can enter a value in the
    material master record. However, it is merely for information.
 
    With automatic reorder point planning and forecast-based planning, the
    system determines and adjusts the value automatically for forecasting
    purposes.
 
MRP 跟安全库存存在一定的联系。
 
一.第一次创建物料
 
如: R999-100 这个物料是我们刚创建的
       Safetty Stock: 100 PC
 
我们用T-Code: MMBE / MB52
 
因为物料是刚创建,肯定是没有库存, 所以库存 是 0 .
 
通过一系列T-Code:  MK01 创建供应商, T-Code: ME11 创建物料清单
 
完成上面的操作后,我们可以通过 T-Code: MD03 创建采购需求
接着 T-Code: MD04  Run MRP , 我们可能到planing order 已经被创建出来,物料需求就等库存 100 PC.
 
以上是为了满足 Safety Stock 保持 100 自动创建物料需求 Run MRP.
 
 
二.当库存被消耗完,低于安全库存
 
假若库存现在  Material Number: R999-100  Qty: 100 PC
 
现在我们用MIGO , Good Issue , Others , Moventy Type: 502   做一次发货,使库存数量低于安全库存,这里我们将库存数库成 0  PC.
 
T-Code: MB51

这里我们再做 MD03 创建物料需求计划, MD04  Run MRP. 可以看到新的planning Order 又产生了.
 
三. 我们也可以通过 加Forecasting 的方法来产生Run MRP请求

T-Code: MD64  给物料加 Forecasting
 
 
接着: T-Code: MD03 
                            MD04
 
 

我们可以看到,也产生了Run MRP 物料需求计划.
 
 
 
 
 
 